September 20, 2023
Virgin Media XGS-PON Installation
Below is a list of the events and the dates as they happened, this is only to provide an estimate of how long it takes from an area going live to a completed install.
- 30th August 2023 - Final Fibre Termination on the Street
- 2nd September 2023 - Available for Ordering
- 5th September 2023 - Service Ordered and Installation Date of the 19th of September given
- 10th September 2023 - External Works done
- 19th September 2023 - Indoor Installation and Activation Completed